Plant Factor, load Factor, load Curve and Reliability Indices
The concept of plant factor, load factor, load curve and the reliability indices of a system are described briefly in this article. Some numerical examples are also given for the sake of better understanding.
Summary
The concept of plant factor, load factor, load curve and the reliability indices of a system are described briefly in this article. Some numerical examples are also given for the sake of better understanding.
Things to Remember
- The students are advised to study the application of plant factor, load factor, load curve and reliability indices.
- Plant factor (PF) = Energy generated/Energy available
- Load factor (LF) = Average load/Peak load
- Loss factor = (0.3 × Load factor) + (0.7) × (Load factor)2
- A numerical example asking the students to determine the reliability indices is always asked in exams.
MCQs
No MCQs found.
Subjective Questions
No subjective questions found.
Videos
No videos found.

Plant Factor, load Factor, load Curve and Reliability Indices
Plant factor
The plant factor, also known as the net capacity factor, of a plant, is defined as the ratio of its actual energy output to its potential output if it is operated continuously at its rated capacity over a period of time.In simple words, it is the ratio of the average demand on the power plant to the maximum installed capacity of the plant.
It is given as,
Plant factor (PF) = Average power demand/Installed capacity of the plant
Multiplying the numerator and denominator by some period of time, we get the relationship in terms of energy as in the original definition as,
PF = Energy generated/Energy available
Numerical example:
The following data of a power plant is given:
Installed capacity of the plant (Preinstalled) = 50 MW
Power demand at the plant (P consumed) = 20 MW
Time of energy consumption (T consumed) = 18 hours
Find the plant factor of the plant.
Solution:
The operation is studied for a period of 24 hours. Therefore in a period of 24 hours,
Energy generated = (Pconsumed × Tconsumed ) = 20 × 18 = 360 MWh
Energy available = ( Pinstalled × 24) = 50 × 24 = 1200 MWh
Then Plant factor is obtained as,
PF = Energy generated/Energy available
= 360/1200
= 0.3
Load factor
Load factor is defined as the ratio of average load to the peak load. It can also be expressed as the ratio of a number of units supplied during a certain period of the maximum energy demand during that period. Load factor refers to the energy load on a system as compared to its peak load for a given period of time and is most typically calculated on a monthly or annual basis.
Load factor is given as,
Load factor (LF) = Average load/Peak load
= No. of energy units supplied during a particular period/Maximum power demand during that period × Period
Loss factor
It is defined as a factor which when multiplied with energy loss at peak time and the number of loads periods gives the overall average energy loss. It is expressed as the ratio of average power loss to the peak power loss or power loss at peak load. If the load to a power plant is constant, throughout the day, the loss factor of the plant is 1. But in practice, the load to a plant varies throughout the day which is given by a load curve.
An approximate value of loss factor can be found by the following equation:
Loss factor = (0.3 × Load factor) + (0.7) × (Load factor)2
Load curve
A load curve, also known as load profile, is a chart illustrating the variation of electrical load over a period of time. Generating companies or electrical utilities use this chart to study the pattern of load variation and to obtain information regarding the amount of power to be generated at a specific time.
An example of a load curve is given in the figure below.

Numerical example:
The load curve of a power plant for a day is shown in the figure below. Calculate the plant factor, load factor, loss factor, and energy loss in a day if the installed capacity of the plant is 150 MW and energy loss at peak load is 10 MW.
Solution:
According to the load curve,
Total units supplied in a day = (50 × 8) + (80 × 4) + (130 × 5) + (60 × 7) = 1790 units
Therefore, average load = 1790/24 = 74.58 MW
Plant factor = Average load/Installed capacity = 74.58/150 = 0.49
Load factor = Average load/Peak load = 74.58/130 = 0.5736
Loss factor = (0.3 × Load factor) + (0.7) × (Load factor)2 = (0.3 × 0.5736) + (0.7) × (0.5736)2 = 0.4023
Actual power loss = Power loss at peak load × Loss factor = 10 × 0.4023 = 4.023
Thus, energy loss in a day (24 Hours) = 24 × 4.023 = 96.552 KWh
Reliability indices
Reliability indices are the parameters or numerical values which are used to determine and describe the performance and reliability of an electric power system. Reliability of a transmission and distribution system refers to the ability of the system to perform its normal functions in both normal and abnormal situations. These indices help us to determine how different components of an interconnected system affect the transmission and distribution of electric power in the whole system. The different reliability indices
SAIDI (System Average Interruption Duration Index)
SAIDI is used by the electric utilities to determine the average cut off or interruption of electric power per customer served. It is obtained as:
SAIDI = (∑ (Duration of trip × No. of consumers affected))/Total consumers
SAIFI (System Average Interruption Frequency Index)
SAIFI is used by the electric utilities to determine the average number of power outages per customer. It is obtained as:
SAIFI = (∑ (No. of trip × No. of consumers affected))/Total consumers
CAIDI (Customer Average Interruption Duration Index)
CAIDI is the ratio of SAIDI to SAIFI and is used by the electric utilities to determine the average power interruption duration that customer experiences. It can also be referred to as average restoration time. It is measured in units of time usually over a course of one year. It is obtained as:
CAIDI = SAIDI/SAIFI
ASAI (Average System Availability Index)
It is used by the electric utilities to determine the average availability of electric power in the system. It is also measured for a course of one year and is obtained as:
ASAI = (8760 × Total consumers - ∑ (Duration of trip × No. of consumers affected))/(Total consumers × 8760)
Example: If the ASAI of a system is 0.9563, it shall be known that electric energy is available in the system 95.63% of the time.
Numerical example:
Calculate all the reliability indices of the distribution system as shown in the diagram below. The number of tripping and trip duration are given for a period of one year. (Asked in 2070 Chaitra)
Solution:
According to the question,
Total number of consumers = Total number of consumers for CB M (N) = 6000
Total number of consumers for CB 1 (NCB1) = 2000
Total number of consumers for CB 2 (NCB2) = 2500
Total number of consumers for CB 3 (NCB3) = 1500
Total number of trips for CB M (TCBM) = 0
Total number of trips for CB 1 (TCB1) = 100
Total number of trips for CB 2 (TCB2) = 75
Total number of trips for CB 3 (TCB3) = 50
Total trip duration for CB M (DCBM) = 0
Total trip duration for CB 1 (DCB1) = 150
Total trip duration for CB 2 (DCB2) = 280
Total trip duration for CB 3 (DCB3) = 140
We have,
SAIFI = (∑ (No. of trip × No. of consumers affected))/Total consumers
= (TCBM × N + TCB1× NCB1 + TCB2× NCB2 + TCB3× NCB3)/N
= (0 × 6000 + 100 × 2000 + 75 × 2500 + 50 × 1500)/6000 = 77.083 trips per customer
SAIDI = (∑ (Duration of trip × No. of consumers affected))/Total consumers
= (DCBM × N + DCB1× NCB1 + DCB2× NCB2 + DCB3× NCB3)/N
= (0 × 6000 + 150 × 2000 + 280 × 2500 + 140 × 1500)/6000 = 201.67 hours per customer
CAIDI = SAIDI/SAIFI = 201.67/77.083 = 2.616 hours per trip
ASAI = (8760 × Total consumers - ∑ (Duration of trip × No. of consumers affected))/(Total consumers × 8760)
= (8760 × 6000 - 1210000)/52560000 = 0.9769 = 97.69%
References
- Wikipedia. (2016). Retrieved from https://www.wikipedia.org/
Information from the handouts provided by my lecturer Mr. Gopal Joshi Subedi has also been used. The numerical problem of reliability indices has been asked in the regular exam of 2070.
The image of the sample load curve was taken from the research article "Journal of Energy in Southern Africa" by Bernard Tembo and Bruno Merven http://www.scielo.org.za/
Lesson
Environmental Concerns,Safety Considerations and Reliability Indices in RE
Subject
Electrical Engineering
Grade
Engineering
Recent Notes
No recent notes.
Related Notes
No related notes.